Supply and installation of a desalination plant, delivered in about four weeks, serving the hospital and its patients.

GazaWater2026

The Moroccan Association for the Support of Reconstruction in Palestine has put water at the top of its interventions in the Gaza Strip. It supported drilling and equipping four wells, supplying water to three areas and providing four generators to run the Beit Lahia municipal well in the north of the Strip, along with projects for maintenance, desalination and drinking water distribution.

4wells drilled and equipped
4generators for the Beit Lahia well
9days to maintain the Amr Ibn Al-As well
3areas supplied with water

Why water?

When wells break down and electricity is cut, getting safe drinking water becomes a daily burden for families, especially in displacement centres. That is why the association and its partners chose to start with water before anything else, and to keep it in focus at every stage.

What has been achieved

Drilling and equipping wells

four wells in the Gaza Strip, including one in Al-Tayeb camp

Well maintenance

maintenance of the Amr Ibn Al-As well was completed in about nine days, from 10 to 18 March 2026

Supplying generators

four generators to run the Beit Lahia municipal well, one of them delivered within a few days

Desalination

a desalination unit at Nasser Hospital, handed over in about four weeks

Water distribution

drinking water delivered by tanker as part of the “Water Relief” campaigns for displaced people

A wider horizon

The executive board had decided to coordinate projects with the diaspora and trustees of the International Commission for Reconstruction, including distributing one million litres of drinking water to displaced people in southern Gaza and one million litres in the north, and maintaining wells in the north of the Strip and equipping them with solar power.

Water remains one of the sectors where the association hopes to expand its partnerships, because its lasting impact goes beyond seasonal relief.

Guarantees written into the contracts

  • A fixed delivery period: 30 days for well contracts
  • Late-delivery penalties and bank guarantees
  • A 12-month maintenance period
  • Workers insured by the contractors
Support this project
Choose an amount, then fill in your details to receive the association’s bank information.

Notice: Test mode is enabled. While in test mode no live donations are processed.

.د.م
Personal Info

التحويل البنكي / Virement bancaire / Bank transfer

الخزينة العامة للمملكة — وكالة الرباط أكدال
Trésorerie Générale du Royaume — Agence Bancaire de Rabat Agdal

RIB : 310 810 1093122704450001 86

بعد التحويل، المرجو إرسال وصل التحويل عبر الواتساب +212 6 61 53 37 34 أو إلى contact@imarpal.ma مع ذكر المشروع المعني.
Après le virement, envoyez le reçu par WhatsApp ou à contact@imarpal.ma en précisant le projet.

Donation Total: ‪250.د.م‬

Support this work

You can support the association’s projects by bank transfer, or contact us on WhatsApp to allocate your contribution.
Treasury General of the Kingdom — Rabat Agdal branch
310 810 1093122704450001 86

Project sheet

  • RegionGaza
  • FieldWater
  • Period2026
  • DeliveryLocal partners

Share this project

Similar projects

Other projects you may like